Northern Ireland’s Central Procurement Directorate issues standard Z clauses for the NEC3
The Central Procurement Directive (CPD) in Northern Ireland has standardised the use of NEC Z clauses for central government construction work in Northern Ireland. The Guidance Note is an extremely valuable resource and is a model of how Z clauses should be incorporated.
Procurement Guidance Note 01/15 dated 8 May 2015 is an excellent example of how Z clauses for the NEC should be incorporated. Z clauses are frequently used to improperly transfer risk or to totally (if unintentionally) confuse the use of the NEC form of contract. However, they are not without merit. With the support of the NEC Users Group and the construction industry parties that engage with them in Northern Ireland, CPD has done a remarkable job of making the process of drafting Z clauses easier.
The Guidance Note is not copyrighted and offers a model for how others can and should adopt Z clauses. It includes a section for 28 typical Z clauses. The Note describes the “purpose” of each clause and gives some guidance as to how it is to be adopted. Some of the clauses are compulsory (for those subject to the Northern Ireland Procurement Policy) and others discretionary.
The Z clauses include many * that are relatively non-contentious and it goes some way to dealing with tricky issues such as two stage contracting (where there is a design which must be accepted before build commences) and the incorporation of a contractor’s quality submissions into the contractual framework.
However, it is arguable that further clarity could have been provided. The document could have:
- Clarified Secondary Option W2 on dispute resolution to make sure that it aligns with the law on adjudication; and
- Removed any ambiguity around the definition of a defect when the problem is the contractors’ service and/or their failure to comply with constraints rather than the actual work done.
Discretionary amendments to the compensation clauses are extremely light touch. There is no standardised amendment to the often changed Clause 19 and the only substantive change to the compensation event system is to move the risk of unforeseen physical conditions in 60.1(12) to the contractor in certain, tightly-defined circumstances.
On the positive side, the control of subcontractors, particularly in relation to those nominated by a contractor in a tendering process, is tightened up and the employer is given an express right to terminate for contraventions of bribery, fraud and the like – although this last point is prefaced as being optional which may cause the employer some difficulties. The “purpose” element of each Z clause, with the corresponding descriptions of intention, could be tightened up to make it clearer when a public authority should use the clauses but there can be absolutely no doubt this is a massive step forward for all in the industry.
The guidance note is essential reading for all NEC3 practitioners and procurers alike.
--Quigg Golden 09:37, 6 July 2015 (BST)
Featured articles and news
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.




















